Pacific Orca safely completes foundation installation on the Borkum Riffgrund 1 wind farm

Fun and impressive project completion facts

  • Installation of 77 full MP/TP foundations
  • Loading of 25,660 mt Transition Pieces
  • Loading of 42,800 mt Mono Pile
  • More than 670 heavy lifts successfully completed
  • MPs piled approx. 2,2 km into the seabed
  • HSE 212,000 SBO hours accumulated

The project was completed safe and efficiently


 