  • MILESTONE REACHED ON GEMINI. CONGRATS TO VAN OORD

31 Aug 2015

Milestone reached on Gemini. Congrats to Van Oord

A milestone has been reached on the Gemini Offshore Wind Park project of the coast of Holland where half of the planned 150 WTG foundations was installed on Friday August 28th 2015.

The foundation comprise of an Mono Pile and a Transition Piece weighing in total approximately 1000 tons. Pacific Osprey has been deployed out of Eemshaven, Holland carrying 3 set of full foundations for one installation cycle.

Swire Blue Ocean vessel Pacific Osprey and Van Oords Aeolus have been installing the impressive number of foundations only since July 1st 2015.

 

News Overview

Pacific Osprey and Pacific Orca received their best eCMID inspection results since construction  20 Apr 2020
New workshop installed on Pacific Orca to facilitate onboard maintenance of nacelles  04 Mar 2020
WindEurope Offshore 2019 is over, see you soon!  16 Dec 2019
Meet us at WindEurope Offshore 2019  18 Nov 2019
SBO exhibits at Offshore Energy 2019 in Amsterdam  30 Oct 2019
SBO participates in the Danish Royal visit to France  28 Oct 2019
SBO Area Manager in Taiwan, Matt Bowden, speaks at the 7th Asia Offshore Wind Day.  24 Oct 2019
Pacific Orca passes by Copenhagen on her way to Wikinger Offshore Windfarm  24 Sep 2019
Let’s stay safe together  28 Aug 2019
SBO has started maintenance and service following recent agreement with Siemens Gamesa Renewable Energy  22 Jul 2019
SBO strengthens business presence in Taiwan with the appointment of new Area Manager, Matt Bowden  30 Apr 2019
Pacific Osprey chartered by GeoSea NV for transport of OTM  27 Mar 2019
SBO installing deepest fixed turbine  25 Feb 2019
Swire Blue Ocean employee killed in Great Belt train accident  11 Jan 2019
Halfway on Beatrice Offshore Wind Farm  21 Dec 2018
A milestone reached on Beatrice Offshore Wind Farm  31 Oct 2018
Exhibiting at the Offshore Energy exhibition, Amsterdam  17 Oct 2018
Beatrice project kicked off to a successful start  03 Jul 2018
Pacific Orca completes installation on the EOWDC  06 Jun 2018
New headquarters  15 Feb 2018
SBO moves to new and bigger facilities  30 Oct 2017
Gemini Offshore Wind Park Completion  01 Sep 2016
Swire Blue Ocean A/S signs contract with Siemens for Beatrice Offshore Windfarm Ltd (BOWL) project  02 Jun 2016
Congrats to Bilfinger with completing Sandbank foundation installation  12 Feb 2016
Milestone reached on Gemini. Congrats to Van Oord  31 Aug 2015
UK Rampion Offshore Wind Farm – we are proud to have been chosen for foundation installation  01 Jun 2015
Decommissioning now also of the Gas Booster Platform B11  23 Feb 2015
New key contract signed with Bilfinger for the Sandbank project  29 Sep 2014
New key contract signed with EPCI contractor Van Oord  19 Sep 2014
Pacific Osprey setting efficiency records with WTG installation on the DanTysk wind farm  30 Aug 2014
Pacific Orca safely completes foundation installation on the Borkum Riffgrund 1 wind farm  29 Jul 2014
First complete WTG installed on DanTysk  10 Apr 2014
BR1 Foundation Installation  27 Jan 2014
Swire Blue Ocean successfully completes H7 decommissioning job  22 Aug 2013
Swire Blue Ocean naming ceremony for Pacific Osprey at Fayard in Denmark  02 Apr 2013
Swire Pacific Offshore takes delivery of world's largest Windfarm Installation Vessel  30 Jul 2012
Second Windfarm Installation Vessel ordered for Swire Blue Ocean A/S  09 Mar 2011
Swire Pacific Offshore acquires Blue Ocean Ships A/S  09 Feb 2011
Swire Blue Ocean is awarded a contract for turbine installation on the DanTysk project  17 Feb 2011
First Windfarm Installation Vessel ordered for Swire Blue Ocean A/S  10 Aug 2010
OFFICES

DENMARK

Swire Blue Ocean A/S
Fairway House
Arne Jacobsens Allé 7
DK-2300 Copenhagen S

Tel : +45 3246 3100
Email: enquiry.DNK@swireblueocean.com 

  

TAIWAN

Swire Blue Ocean
12th Floor, No. 129, Minsheng E. Rd, Section 3
Songshan District
Taipei City

Tel: +886 9 5583 9202
Email: enquiry.TWN@swireblueocean.com