M
  • NEW HEADQUARTERS

15 Feb 2018

New headquarters

As previously announced, we are moving our headquarters to a new spacious location to accommodate the expansion of staff and business projects. We are not moving far, however; approximately 600 meters from our old home.


Oerestad has been good to us since we moved here in 2011, with its strong winds and lofty skies in the middle of a fairly new part of Copenhagen.
With the close proximity to both Copenhagen Airport, the Metro and Copenhagen City, this location fits us perfectly and we look forward to welcoming our guests in the new surroundings.


From Monday February 19th 2018 our address is:

Swire Blue Ocean A/S
Fairway House
Arne Jacobsens Allé 7, 7th Floor
DK-2300 Copenhagen S

News

Pacific Orca passes by Copenhagen on her way to Wikinger Offshore Windfarm  24 Sep 2019
Let’s stay safe together  28 Aug 2019
SBO has started maintenance and service following recent agreement with Siemens Gamesa Renewable Energy  22 Jul 2019
SBO strengthens business presence in Taiwan with the appointment of new Area Manager, Matt Bowden  30 Apr 2019
Pacific Osprey chartered by GeoSea NV for transport of OTM  27 Mar 2019
SBO installing deepest fixed turbine  25 Feb 2019
Swire Blue Ocean employee killed in Great Belt train accident  11 Jan 2019
Halfway on Beatrice Offshore Wind Farm  21 Dec 2018
A milestone reached on Beatrice Offshore Wind Farm  31 Oct 2018
Exhibiting at the Offshore Energy exhibition, Amsterdam  17 Oct 2018
Media Update – 27th August 2018, 11:00 CET  27 Aug 2018
Press Update – 24th August 2018, 14:00 CET  24 Aug 2018
Beatrice project kicked off to a successful start  03 Jul 2018
Pacific Orca completes installation on the EOWDC  06 Jun 2018
Grand Opening Event  15 Apr 2018
New headquarters  15 Feb 2018
Appointment of Mikkel Gleerup as Chief Executive Officer  12 Feb 2018
Lars Blicher retires from Swire Blue Ocean A/S  02 Jan 2018
SBO moves to new and bigger facilities  02 Jan 2018
Gemini Offshore Wind Park Completion  02 Jan 2018
Swire Blue Ocean A/S signs contract with Siemens for Beatrice Offshore Windfarm Ltd (BOWL) project  03 Jan 2018
Congrats to Bilfinger with completing Sandbank foundation installation  03 Jan 2018
OFFICES

DENMARK

Swire Blue Ocean A/S
Fairway House
Arne Jacobsens Allé 7
DK-2300 Copenhagen S

Tel : +45 3246 3100

Email: enquiry.DNK@swireblueocean.com 
(for general contact)

  

TAIWAN

Swire Blue Ocean
12th Floor, No. 129, Minsheng E. Rd, Section 3
Songshan District
Taipei City

Tel: +886 9 5583 9202